Frederick House – St Vincent De Paul Society

Project Info

Project Description

Project Duration: 2 weeks

Project completion date: 4 August 2018

RBS were commissioned to perform a hammer test to the façade and ascertain locations that requires repair including but not limited to render, concrete spalling and water ingress concerns.

A defect mapping schedule was prepared and submitted to the client and a cost for repair was submitted.

 

The works consisted of:

  1. Render rectification
  2. Concrete Spalling
  3. Façade coating
  4. Brickwork rectification